This photo shows the second floor joists in place. The plywood sub floor boards will be placed on top of the joists, the beginning of which can be seen in the left part of the photo. |
Ditto |
Designer, Luther Allen, and site manager, Dylan Hicks, determining the feasibility of adding soffit framing to the pre-fabricated roof trusses. |
Ditto. Dylan had drawn a sketch comparing pre-fabricated soffits with "stick" frame soffits to help us decide if the pre-fabricated soffits would work. The conclusion was that they would. |
Ditto. |
The two stacks of walls in the lower half of this photo are the exterior walls of the second story. The stack of walls in the upper center of the photo are the interior walls. |
When all the walls had been lifted to the second story, the crane lifted a final load of bundled 2x6s to be used in connecting the walls. |
Daniel and Casey prepare the bedroom floor for the first wall. |
Dylan joined the group for the delicate process of raising the wall and putting it exactly in place. In this photo, left to right, are Dylan, Casey, Daniel, and Mike. |
Several hundred pounds of wall begin to rise. |
Ditto |
The wall has been maneuvered into its correct location and is now temporarily secured by 2x4 braces. |
Ditto |
The walls had been delivered around noon. This photo shows that by the end of the first day, the crew had installed all three exterior walls of the bedroom. Not a bad afternoon's work! |
The view at the end of this day from the backyard |
This photo shows the west side of the house with the last three sections yet to be installed. |
Looking north, the crew begins to install a few interior walls to help brace the entire structure. |
Ditto |
In addition, Daniel installs 2x6 top plates around the entire perimeter to tie each wall section to the sections on either side of it. |
Daniel, Casey, and Mike lifting the first of the remaining exterior walls |
Ditto |
This is the penultimate wall. |
The penultimate wall being lifted into place. This photo shows how precarious it is to place the wall section exactly at the edge of the building. No room for error! |
The penultimate section is in place. One to go. |
This photo shows the final space and final exterior wall. |
Mike is double checking the measurements to be absolutely sure that the window in this final section lines up perfectly with the window below. |
From left to right, Casey, Mike, and Daniel begin lifting the final wall. |
While Daniel and Mike hold the final wall in place, Casey taps the base with a sledge hammer to bring the base into exact alignment with the blue snap line. |
The BB arrives at the second floor via the temporary staircase. |
Mike, below, and Daniel , on the ladder, working on the interior walls |
A view of the rear of the house with all exterior walls installed |
The house was tarped in anticipation that there might be some "showers." |
Ditto |
The BB and designer, Luther Allen, check out the rooms that have materialized now that the interior walls are all in place. |
This is how the house looked at the end of the week, just in time for the anticipated showers. In the Northwest, showers sometimes means gully washers. Today was one of those gully washers. |
The bedroom floor soaked with rain. This part of the building was not tarped because the rain doesn't produce any long-term adverse effects to the timbers at this stage of construction. |
As the day wore on, we decided to elevate our spa and also decorate the area with a falling ceiling motif. The BB checks the temperature of the spa water. |
No comments:
Post a Comment